Hey Cornerstone! Most of you know that we started our bathroom remodel project last Sunday. Our goal was to complete most of it by Saturday, August 13th. We have had a team of people working constantly, working 12-14 hour days. We’ve accomplished a lot, but the project is not finished. As with most remodel projects, there are unknown “surprises” in the process. We are really only one day behind, but that will make an impact for our services tomorrow. This is to let you know our situation and what to expect bathroomwise. For guys especially, be aware of what the situation is.
Women’s restroom: The women’s restroom is 85% complete and 100% usable. All stalls and the sink are working perfectly.
Yet to be installed: Light fixture, toilet paper holders, hooks, baby changing table (there is one available in the nursery). There is still some trim work to do as well (cosmetic only).
Men’s restroom: The men’s restroom is about 50% complete and 25% usable. The urinal and both toilets are working. There NO partitions.
Yet to be installed: Partitions, sink, light fixture and almost all trim.
Solutions for guys: We will have a table with hand sanitizer in the restroom. There is also a sink across the hall in the furnace room. The nursery restroom will be available; but be aware that it is one-at-a-time and very small.
We expect everything to be completed by Sunday August 21st.
Thanks for your patience and understanding.